FERC Calls BPA’s High Water/Wind Power Cutoff Rule Discriminatory, Orders Correction In 90 Days

The Federal Energy Regulatory Commission sided with wind generating companies in a Wednesday order giving the Bonneville Power Administration 90 days to correct what the commission called an “unduly discriminatory” policy limiting transmission of wind, thermal and other non-hydro power during high water flows in the Columbia River basin.

Read the full article…

Become a Member and get unlimited access to all articles.

Register

Already a member? Log in here

More news from CBB: